IN PROGRESS

  • West Hauling Company New Build
  • East Hauling Company New Build
  • Midwest Maintenance Shop Remodel
  • Midwest Hauling Company New Build

UPCOMING PROJECTS!

  • Midwest Shop Expansion
  • Midwest Transfer Station New Build
  • Material Recovery Facility New Build
  • West Processing Facility New Build

WORK-IN-PROGRESS

Progress photos from the remodel of an existing facility, addition of new buildings, and site improvements.

Update (12/23):

Cambridge’s Project #1: Hauling Company Work in Progress update

The finishing touches are underway at the Hauling Company!  Hose reels in the maintenance shop are installed and the mounting racks are painted; the office walls are being taped and prepped for painting; the compressor lean-to building trim has been installed; the parts room light fixtures have been installed and are working; joint cuts have been completed in the concrete at the fuel island; and the soffit has been installed at the fuel island canopy.  Only a few more things to be done at this site before our final post!  Check back here for the final progress on the Hauling Company project!  🏭🔶🛠1️

Previous
Next
Show more
Project #1 (11/29): Exterior Lighting Installed

Project #1 (11/29): Exterior Lighting Installed

Show more
Project #1 (11/29): South Lot Paved and Striped

Project #1 (11/29): South Lot Paved and Striped

Show more
Project #1 (11/29): Polishing Bay Floors

Project #1 (11/29): Polishing Bay Floors

Show more
Project #1 (11/29): Fuel Island Installation Continues

Project #1 (11/29): Fuel Island Installation Continues

Show more
Project #1 (11/29): Tank Installation

Project #1 (11/29): Tank Installation

Show more
Project #1 (11/29): Office Studs and Roof Decking Installation

Project #1 (11/29): Office Studs and Roof Decking Installation

Show more
Project #1 (11/8): Fuel Island Canopy Installation Began

Project #1 (11/8): Fuel Island Canopy Installation Began

Show more
Project #1 (11/8): Fuel Island Forms Removed

Project #1 (11/8): Fuel Island Forms Removed

Show more
Project #1 (11/8): Polished Floors and Completed Bays in Addition

Project #1 (11/8): Polished Floors and Completed Bays in Addition

Show more
Project #1 (11/8): Wash Bay Floor before Seal Completed

Project #1 (11/8): Wash Bay Floor before Seal Completed

Show more
Project #1 (11/8): Exterior Fixtures and Photo Sensors Installation

Project #1 (11/8): Exterior Fixtures and Photo Sensors Installation

Show more
Project #1 (10/19): Concrete poured and control joints cut

Project #1 (10/19): Concrete poured and control joints cut

Show more
Project #1 (10/19): Sprinkler and big fan installed in shop addition

Project #1 (10/19): Sprinkler and big fan installed in shop addition

Show more
Project #1 (10/19): Red light/green light switches installed (exterior)

Project #1 (10/19): Red light/green light switches installed (exterior)

Show more
Project #1 (10/19): Wash Bay nearly completed

Project #1 (10/19): Wash Bay nearly completed

Show more
Project #1 (10/19): Equipment Room air and conduit lines installed and equipment moved in

Project #1 (10/19): Equipment Room air and conduit lines installed and equipment moved in

Show more
Project #1 (10/19): Fuel Island installation has begun

Project #1 (10/19): Fuel Island installation has begun

Show more
Project #1 (9/24): Pile of Concrete Removed from North Drive

Project #1 (9/24): Pile of Concrete Removed from North Drive

Show more
Project #1 (9/24): L.P Tank Pad Pre-Pour Bollards

Project #1 (9/24): L.P Tank Pad Pre-Pour Bollards

Show more
Project #1 (9/24): Installing Overhead Door Panels

Project #1 (9/24): Installing Overhead Door Panels

Show more
Project #1 (9/24): Working on South Overhead Door Tracks

Project #1 (9/24): Working on South Overhead Door Tracks

Show more
Project #1 (9/24): View of Conduit Bank on Westside Addition

Project #1 (9/24): View of Conduit Bank on Westside Addition

Show more
Project #1 (9/3): Overhead Door Framing

Project #1 (9/3): Overhead Door Framing

Show more
Project #1 (9/3): Power Trowel Paving

Project #1 (9/3): Power Trowel Paving

Show more
Project #1 (9/3): Pre-Paving Concrete Pour

Project #1 (9/3): Pre-Paving Concrete Pour

Show more
Project #1 (9/3): Loading out Spoils

Project #1 (9/3): Loading out Spoils

Show more
Project #1 (9/3): New Wash Bay Addition and Site Paving

Project #1 (9/3): New Wash Bay Addition and Site Paving

Progress photos from the new build of a maintenance shop.

Update (1/7):

Cambridge Project #2: Maintenance Shop Work in Progress update:

Progress continues on this maintenance shop into the new year!  The roll up doors in the parts room have been installed; doors, frames, and hardware have been installed in the Office Area; the drywall in the Office Area has been completed; column framing in the parts room has been completed; ceiling grid is ready to be installed in the break room; and the enclosed services counter has been installed.

Previous
Next
Show more
Project #2 (1/7): Coiling Door Installed in Parts Room

Project #2 (1/7): Coiling Door Installed in Parts Room

Show more
Project #2 (1/7): Doors, Frames & Hardware Installed

Project #2 (1/7): Doors, Frames & Hardware Installed

Show more
Project #2 (1/7): Drywall Completed

Project #2 (1/7): Drywall Completed

Show more
Project #2 (1/7): Column Framing in Parts Room

Project #2 (1/7): Column Framing in Parts Room

Show more
Project #2 (1/7): Preparing for Ceiling Grid in Break Room

Project #2 (1/7): Preparing for Ceiling Grid in Break Room

Show more
Project #2 (1/7): Enclosed Service Counter Installed

Project #2 (1/7): Enclosed Service Counter Installed

Show more
Project #2 (12/18): Aerial View of the Site and Facility Progress

Project #2 (12/18): Aerial View of the Site and Facility Progress

Show more
Project #2 (12/18): Siding Installation on Metal Building Progress

Project #2 (12/18): Siding Installation on Metal Building Progress

Show more
Project #2 (12/18): Ductwork being Installed

Project #2 (12/18): Ductwork being Installed

Show more
Project #2 (12/18): Framing Installation of Office Section

Project #2 (12/18): Framing Installation of Office Section

Show more
Project #2 (12/18): Drywall beginning to be Installed

Project #2 (12/18): Drywall beginning to be Installed

Show more
Project #2 (12/18): Masonry Work

Project #2 (12/18): Masonry Work

Show more
Project #2 (11/15): Exterior of Office Trim Started

Project #2 (11/15): Exterior of Office Trim Started

Show more
Project #2 (11/15): Interior Wall Framing and Blocking

Project #2 (11/15): Interior Wall Framing and Blocking

Show more
Project #2 (11/15): Shop View of Masonry Separation Wall

Project #2 (11/15): Shop View of Masonry Separation Wall

Show more
Project #2 (11/15): Future Parts Room View into the Future Shop

Project #2 (11/15): Future Parts Room View into the Future Shop

Show more
Project #2 (11/15): Another Section of Truck Parking Poured

Project #2 (11/15): Another Section of Truck Parking Poured

Show more
Project #2 (11/15): Progress in the Truck Parking Lot Concrete

Project #2 (11/15): Progress in the Truck Parking Lot Concrete

Show more
Project #2 (10/25): Sheeting being laid on metal building roof

Project #2 (10/25): Sheeting being laid on metal building roof

Show more
Project #2 (10/25): Site graded with mesh laid for concrete pour

Project #2 (10/25): Site graded with mesh laid for concrete pour

Show more
Project #2 (10/25): Curbs laid out on shop flooring

Project #2 (10/25): Curbs laid out on shop flooring

Show more
Project #2 (10/25): Employee parking area concrete poured and control joints cut

Project #2 (10/25): Employee parking area concrete poured and control joints cut

Show more
Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Show more
Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Show more
Project #2 (10/3): Maintenance Shop Aerial September 2018

Project #2 (10/3): Maintenance Shop Aerial September 2018

Show more
Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Show more
Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Show more
Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Show more
Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Show more
Project #2 (10/3): Brooming Concrete Employee Parking Lot

Project #2 (10/3): Brooming Concrete Employee Parking Lot

Show more
Project #2 (9/10): Office Building Parking Area

Project #2 (9/10): Office Building Parking Area

Show more
Project #2 (9/10): Placing Aggregate Base

Project #2 (9/10): Placing Aggregate Base

Show more
Project #2 (9/10): Vapor Barrier And Rebar Installation

Project #2 (9/10): Vapor Barrier And Rebar Installation

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Progress photos from the truck maintenance shop.

Update (12/17):

Cambridge’s Project #3: Maintenance Shop Work in Progress update:

Only one more post left on the completion of the renovation and addition to this maintenance shop!  Fencing on the site, surrounding the facility is installed; overhead doors fully installed; lighting installed in the new service bays and existing services area; trench drains being installed for excess fluid during vehicle maintenance and cleaning of the facility; and tile installation nearly complete in the office areas.

Previous
Next
Show more
Project #3 (12/20): East Side West Gate Installed

Project #3 (12/20): East Side West Gate Installed

Show more
Project #3 (12/20): West Side Overhead Doors Installed

Project #3 (12/20): West Side Overhead Doors Installed

Show more
Project #3 (12/20): New Lights Installed in Existing Services Bays

Project #3 (12/20): New Lights Installed in Existing Services Bays

Show more
Project #3 (12/20): Concrete Removal for New Trench Drain

Project #3 (12/20): Concrete Removal for New Trench Drain

Show more
Project #3 (12/20): Hallway Tile Installation

Project #3 (12/20): Hallway Tile Installation

Show more
Project #3 (11/21): Overhead Door Install in Existing Shop

Project #3 (11/21): Overhead Door Install in Existing Shop

Show more
Project #3 (11/21): Ductwork Installed in Existing Shop

Project #3 (11/21): Ductwork Installed in Existing Shop

Show more
Project #3 (11/21): Truck Exhaust Modifications in Existing Shop

Project #3 (11/21): Truck Exhaust Modifications in Existing Shop

Show more
Project #3 (11/21): Hose Reels Installed in Shop Addition

Project #3 (11/21): Hose Reels Installed in Shop Addition

Show more
Project #3 (11/21): Hose Reels Installed in Shop Addition

Project #3 (11/21): Hose Reels Installed in Shop Addition

Show more
Project #3 (11/21): HVAC Installed

Project #3 (11/21): HVAC Installed

Show more
Project #3 (11/21): Drywall Install in Office Renovation

Project #3 (11/21): Drywall Install in Office Renovation

Show more
Project #3 (11/2): Office Tile Demo

Project #3 (11/2): Office Tile Demo

Show more
Project #3 (11/2): New Framing Installed

Project #3 (11/2): New Framing Installed

Show more
Project #3 (11/2): Parts Room complete

Project #3 (11/2): Parts Room complete

Show more
Project #3 (11/2): Stripped Curb in Parking Lot

Project #3 (11/2): Stripped Curb in Parking Lot

Show more
Project #3 (11/2): View of the Retention Pond

Project #3 (11/2): View of the Retention Pond

Show more
Project #3 (11/2): Spreading Stone Base prior to Asphalt Pour

Project #3 (11/2): Spreading Stone Base prior to Asphalt Pour

Show more
Project #3 (10/9): Apron Grading

Project #3 (10/9): Apron Grading

Show more
Project #3 (10/9): Completed Washroom

Project #3 (10/9): Completed Washroom

Show more
Project #3 (10/9): Completed Break Room

Project #3 (10/9): Completed Break Room

Show more
Project #3 (10/9): Completed Locker Room

Project #3 (10/9): Completed Locker Room

Show more
Project #3 (10/9): Parking Lot Demo

Project #3 (10/9): Parking Lot Demo

Show more
Project #3 (10/9): Storm Water Installation

Project #3 (10/9): Storm Water Installation