IN PROGRESS

  • West Hauling Company New Build
  • East Hauling Company New Build
  • Midwest Maintenance Shop Remodel
  • Midwest Hauling Company New Build

UPCOMING PROJECTS!

  • Midwest Shop Expansion
  • Midwest Transfer Station New Build
  • Material Recovery Facility New Build
  • West Processing Facility New Build

WORK-IN-PROGRESS

Progress photos from the remodel of an existing facility, addition of new buildings, and site improvements.

Update (1/23):

Cambridge’s Project #1: Hauling Company Work in Progress update

The maintenance shop continues to make progress toward our final post!  The guardrail and gates looking east have been installed; bollards have been painted around the service disconnects; wires have been pulled for the fuel island dispensers; the FuelMaster® reader has been installed; and the fuel island is nearing full completion!

Previous
Next
Show more
Project #1 (1/23): Guardrail and gates looking east

Project #1 (1/23): Guardrail and gates looking east

Show more
Project #1 (1/23): Bollards painted around service disconnects

Project #1 (1/23): Bollards painted around service disconnects

Show more
Project #1 (1/23): Pulling wires for dispensers

Project #1 (1/23): Pulling wires for dispensers

Show more
Project #1 (1/23): FuelMaster® reader

Project #1 (1/23): FuelMaster® reader

Show more
Project #1 (1/23): Fuel Island

Project #1 (1/23): Fuel Island

Show more
Project #1 (11/29): Exterior Lighting Installed

Project #1 (11/29): Exterior Lighting Installed

Show more
Project #1 (11/29): South Lot Paved and Striped

Project #1 (11/29): South Lot Paved and Striped

Show more
Project #1 (11/29): Polishing Bay Floors

Project #1 (11/29): Polishing Bay Floors

Show more
Project #1 (11/29): Fuel Island Installation Continues

Project #1 (11/29): Fuel Island Installation Continues

Show more
Project #1 (11/29): Tank Installation

Project #1 (11/29): Tank Installation

Show more
Project #1 (11/29): Office Studs and Roof Decking Installation

Project #1 (11/29): Office Studs and Roof Decking Installation

Show more
Project #1 (11/8): Fuel Island Canopy Installation Began

Project #1 (11/8): Fuel Island Canopy Installation Began

Show more
Project #1 (11/8): Fuel Island Forms Removed

Project #1 (11/8): Fuel Island Forms Removed

Show more
Project #1 (11/8): Polished Floors and Completed Bays in Addition

Project #1 (11/8): Polished Floors and Completed Bays in Addition

Show more
Project #1 (11/8): Wash Bay Floor before Seal Completed

Project #1 (11/8): Wash Bay Floor before Seal Completed

Show more
Project #1 (11/8): Exterior Fixtures and Photo Sensors Installation

Project #1 (11/8): Exterior Fixtures and Photo Sensors Installation

Show more
Project #1 (10/19): Concrete poured and control joints cut

Project #1 (10/19): Concrete poured and control joints cut

Show more
Project #1 (10/19): Sprinkler and big fan installed in shop addition

Project #1 (10/19): Sprinkler and big fan installed in shop addition

Show more
Project #1 (10/19): Red light/green light switches installed (exterior)

Project #1 (10/19): Red light/green light switches installed (exterior)

Show more
Project #1 (10/19): Wash Bay nearly completed

Project #1 (10/19): Wash Bay nearly completed

Show more
Project #1 (10/19): Equipment Room air and conduit lines installed and equipment moved in

Project #1 (10/19): Equipment Room air and conduit lines installed and equipment moved in

Show more
Project #1 (10/19): Fuel Island installation has begun

Project #1 (10/19): Fuel Island installation has begun

Show more
Project #1 (9/24): Pile of Concrete Removed from North Drive

Project #1 (9/24): Pile of Concrete Removed from North Drive

Show more
Project #1 (9/24): L.P Tank Pad Pre-Pour Bollards

Project #1 (9/24): L.P Tank Pad Pre-Pour Bollards

Show more
Project #1 (9/24): Installing Overhead Door Panels

Project #1 (9/24): Installing Overhead Door Panels

Show more
Project #1 (9/24): Working on South Overhead Door Tracks

Project #1 (9/24): Working on South Overhead Door Tracks

Show more
Project #1 (9/24): View of Conduit Bank on Westside Addition

Project #1 (9/24): View of Conduit Bank on Westside Addition

Show more
Project #1 (9/3): Overhead Door Framing

Project #1 (9/3): Overhead Door Framing

Show more
Project #1 (9/3): Power Trowel Paving

Project #1 (9/3): Power Trowel Paving

Show more
Project #1 (9/3): Pre-Paving Concrete Pour

Project #1 (9/3): Pre-Paving Concrete Pour

Show more
Project #1 (9/3): Loading out Spoils

Project #1 (9/3): Loading out Spoils

Show more
Project #1 (9/3): New Wash Bay Addition and Site Paving

Project #1 (9/3): New Wash Bay Addition and Site Paving

Progress photos from the new build of a maintenance shop.

Update (2/14):

Cambridge Project #2: Maintenance Shop Work in Progress update:

Work on this maintenance shop continue to move smoothly during these bitterly cold, arctic blast months!  Progress includes the roof drain stubs completed; entry door trim installed; final door panels installed on the east side; water lines dug and being installed; t-bar grid in the break room ceiling installed; conduits running to the shop installed; and the transfer and pad installe

Previous
Next
Show more
Project #2 (2/14): Roof Drain Stubs

Project #2 (2/14): Roof Drain Stubs

Show more
Project #2 (2/14): Entry Door Trim Installed

Project #2 (2/14): Entry Door Trim Installed

Show more
Project #2 (2/14): Final Door Panels Installed on the East Side

Project #2 (2/14): Final Door Panels Installed on the East Side

Show more
Project #2 (2/14): Water Lines Dug and Being Installed

Project #2 (2/14): Water Lines Dug and Being Installed

Show more
Project #2 (2/14): T-bar Grid in the Break Room Installed

Project #2 (2/14): T-bar Grid in the Break Room Installed

Show more
Project #2 (2/14): Conduits Run to the Shop

Project #2 (2/14): Conduits Run to the Shop

Show more
Project #2 (2/14): Transformer and Pad Installed

Project #2 (2/14): Transformer and Pad Installed

Show more
Project #2 (1/7): Coiling Door Installed in Parts Room

Project #2 (1/7): Coiling Door Installed in Parts Room

Show more
Project #2 (1/7): Doors, Frames & Hardware Installed

Project #2 (1/7): Doors, Frames & Hardware Installed

Show more
Project #2 (1/7): Drywall Completed

Project #2 (1/7): Drywall Completed

Show more
Project #2 (1/7): Column Framing in Parts Room

Project #2 (1/7): Column Framing in Parts Room

Show more
Project #2 (1/7): Preparing for Ceiling Grid in Break Room

Project #2 (1/7): Preparing for Ceiling Grid in Break Room

Show more
Project #2 (1/7): Enclosed Service Counter Installed

Project #2 (1/7): Enclosed Service Counter Installed

Show more
Project #2 (12/18): Aerial View of the Site and Facility Progress

Project #2 (12/18): Aerial View of the Site and Facility Progress

Show more
Project #2 (12/18): Siding Installation on Metal Building Progress

Project #2 (12/18): Siding Installation on Metal Building Progress

Show more
Project #2 (12/18): Ductwork being Installed

Project #2 (12/18): Ductwork being Installed

Show more
Project #2 (12/18): Framing Installation of Office Section

Project #2 (12/18): Framing Installation of Office Section

Show more
Project #2 (12/18): Drywall beginning to be Installed

Project #2 (12/18): Drywall beginning to be Installed

Show more
Project #2 (12/18): Masonry Work

Project #2 (12/18): Masonry Work

Show more
Project #2 (11/15): Exterior of Office Trim Started

Project #2 (11/15): Exterior of Office Trim Started

Show more
Project #2 (11/15): Interior Wall Framing and Blocking

Project #2 (11/15): Interior Wall Framing and Blocking

Show more
Project #2 (11/15): Shop View of Masonry Separation Wall

Project #2 (11/15): Shop View of Masonry Separation Wall

Show more
Project #2 (11/15): Future Parts Room View into the Future Shop

Project #2 (11/15): Future Parts Room View into the Future Shop

Show more
Project #2 (11/15): Another Section of Truck Parking Poured

Project #2 (11/15): Another Section of Truck Parking Poured

Show more
Project #2 (11/15): Progress in the Truck Parking Lot Concrete

Project #2 (11/15): Progress in the Truck Parking Lot Concrete

Show more
Project #2 (10/25): Sheeting being laid on metal building roof

Project #2 (10/25): Sheeting being laid on metal building roof

Show more
Project #2 (10/25): Site graded with mesh laid for concrete pour

Project #2 (10/25): Site graded with mesh laid for concrete pour

Show more
Project #2 (10/25): Curbs laid out on shop flooring

Project #2 (10/25): Curbs laid out on shop flooring

Show more
Project #2 (10/25): Employee parking area concrete poured and control joints cut

Project #2 (10/25): Employee parking area concrete poured and control joints cut

Show more
Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Show more
Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Show more
Project #2 (10/3): Maintenance Shop Aerial September 2018

Project #2 (10/3): Maintenance Shop Aerial September 2018

Show more
Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Show more
Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Show more
Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Show more
Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Show more
Project #2 (10/3): Brooming Concrete Employee Parking Lot

Project #2 (10/3): Brooming Concrete Employee Parking Lot

Show more
Project #2 (9/10): Office Building Parking Area

Project #2 (9/10): Office Building Parking Area

Show more
Project #2 (9/10): Placing Aggregate Base

Project #2 (9/10): Placing Aggregate Base

Show more
Project #2 (9/10): Vapor Barrier And Rebar Installation

Project #2 (9/10): Vapor Barrier And Rebar Installation

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Progress photos from the truck maintenance shop.

Update (2/20):

Cambridge’s Project #3: Maintenance Shop Work in Progress update:

Last post on the progress of this maintenance shop until our final photo shoot in May!  Our Field Manager is completing the final Punchlist items for turn over to the client including adding emergency lighting required by the AHJ, completing lube reel installation in the existing shop, and installing additional truck exhaust hoses.  The under-mezzanine sprinkler pipe has been installed and both entrances are now open.  Thank you to the project team and everyone who worked to make this a successful project!

Previous
Next
Show more
Project #3 (2/20): Above Mezzanine Emergency Lighting

Project #3 (2/20): Above Mezzanine Emergency Lighting

Show more
Project #3 (2/20): Stairwell Emergency Lighting

Project #3 (2/20): Stairwell Emergency Lighting

Show more
Project #3 (2/20): Driver's Waiting Room Door Installed

Project #3 (2/20): Driver’s Waiting Room Door Installed

Show more
Project #3 (2/20): Under-Mezzanine Sprinkler Pipe Installed

Project #3 (2/20): Under-Mezzanine Sprinkler Pipe Installed

Show more
Project #3 (2/20): Middle Lube Reel in Existing Shop Installed

Project #3 (2/20): Middle Lube Reel in Existing Shop Installed

Show more
Project #3 (2/20): Front of Building Looking West

Project #3 (2/20): Front of Building Looking West

Show more
Project #3 (12/20): East Side West Gate Installed

Project #3 (12/20): East Side West Gate Installed

Show more
Project #3 (12/20): West Side Overhead Doors Installed

Project #3 (12/20): West Side Overhead Doors Installed

Show more
Project #3 (12/20): New Lights Installed in Existing Services Bays

Project #3 (12/20): New Lights Installed in Existing Services Bays

Show more
Project #3 (12/20): Concrete Removal for New Trench Drain

Project #3 (12/20): Concrete Removal for New Trench Drain

Show more
Project #3 (12/20): Hallway Tile Installation

Project #3 (12/20): Hallway Tile Installation

Show more
Project #3 (11/21): Overhead Door Install in Existing Shop

Project #3 (11/21): Overhead Door Install in Existing Shop

Show more
Project #3 (11/21): Ductwork Installed in Existing Shop

Project #3 (11/21): Ductwork Installed in Existing Shop

Show more
Project #3 (11/21): Truck Exhaust Modifications in Existing Shop

Project #3 (11/21): Truck Exhaust Modifications in Existing Shop

Show more
Project #3 (11/21): Hose Reels Installed in Shop Addition

Project #3 (11/21): Hose Reels Installed in Shop Addition

Show more
Project #3 (11/21): Hose Reels Installed in Shop Addition

Project #3 (11/21): Hose Reels Installed in Shop Addition

Show more
Project #3 (11/21): HVAC Installed

Project #3 (11/21): HVAC Installed

Show more
Project #3 (11/21): Drywall Install in Office Renovation

Project #3 (11/21): Drywall Install in Office Renovation

Show more
Project #3 (11/2): Office Tile Demo

Project #3 (11/2): Office Tile Demo

Show more
Project #3 (11/2): New Framing Installed

Project #3 (11/2): New Framing Installed

Show more
Project #3 (11/2): Parts Room complete

Project #3 (11/2): Parts Room complete

Show more
Project #3 (11/2): Stripped Curb in Parking Lot

Project #3 (11/2): Stripped Curb in Parking Lot

Show more
Project #3 (11/2): View of the Retention Pond

Project #3 (11/2): View of the Retention Pond

Show more
Project #3 (11/2): Spreading Stone Base prior to Asphalt Pour

Project #3 (11/2): Spreading Stone Base prior to Asphalt Pour

Show more
Project #3 (10/9): Apron Grading

Project #3 (10/9): Apron Grading

Show more
Project #3 (10/9): Completed Washroom

Project #3 (10/9): Completed Washroom

Show more
Project #3 (10/9): Completed Break Room

Project #3 (10/9): Completed Break Room

Show more
Project #3 (10/9): Completed Locker Room

Project #3 (10/9): Completed Locker Room

Show more
Project #3 (10/9): Parking Lot Demo

Project #3 (10/9): Parking Lot Demo

Show more
Project #3 (10/9): Storm Water Installation

Project #3 (10/9): Storm Water Installation