IN PROGRESS

  • Midwest Transfer Station New Build
  • East Processing Facility Improvements
  • South Hauling Facility Site Improvements
  • Processing Facility Remodel (complete)

UPCOMING PROJECTS!

  • Southwest Maintenance Shop
  • West Transfer Station New Build
  • Northwest Processing Facility
  • West Recycling Processing Facility
  • West Transfer Station
  • Midwest Recycling Facility
  • East Resource Recovery Facility
  • Southwest Maintenance Shop Improvements

WORK-IN-PROGRESS

Update (2/21):

Cambridge Project #7: Compactor Repair Shop

Nearing completion this month, the Compactor Repair Shop and other facility work continues to move forward.  The Compactor/Container Repair Workstations have been completed, the electrical distribution service established, dividing walls & paneling completed, & final paint touch up has begun.  Ductwork for the new paint booth is close to complete & the client is starting to prepare for operations.  Cambridge plans to demobilize in March once the Punch List process is complete & the client is satisfied.

#compactor #repair #constructioninprocess

Previous
Next
Show more
Project #8 (2/21): New Wash Bay Complete

Project #8 (2/21): New Wash Bay Complete

Show more
Project #8 (2/21): New Ramp & Staging Area Complete for Paint Booth

Project #8 (2/21): New Ramp & Staging Area Complete for Paint Booth

Show more
Project #8 (2/21): New Shop Electrical Service and Distribution Complete

Project #8 (2/21): New Shop Electrical Service and Distribution Complete

Show more
Project #8 (2/21): Electrical Complete at Large Workstations

Project #8 (2/21): Electrical Complete at Large Workstations

Show more
Project #8 (2/21): Electric Complete at Small Workstations

Project #8 (2/21): Electric Complete at Small Workstations

Show more
Project #8 (2/21): Installing Ductwork at Paint Booth

Project #8 (2/21): Installing Ductwork at Paint Booth

Show more
Project #8 (11/18): Demolition & Removal of Existing Concrete for New Workstations

Project #8 (11/18): Demolition & Removal of Existing Concrete for New Workstations

Show more
Project #8 (11/18): Preparing Subgrade for New Concrete Ramp

Project #8 (11/18): Preparing Subgrade for New Concrete Ramp

Show more
Project #8 (11/18): Demolition & Removal of Existing Concrete for New Ramp

Project #8 (11/18): Demolition & Removal of Existing Concrete for New Ramp

Show more
Project #8 (11/18): Pouring New Concrete Ramp

Project #8 (11/18): Pouring New Concrete Ramp

Show more
Project #8 (11/18): Infill of Existing Pit

Project #8 (11/18): Infill of Existing Pit

Show more
Project #8 (11/18): New Slab Poured at Storage Area

Project #8 (11/18): New Slab Poured at Storage Area

Show more
Project #8 (11/18): Pouring New Concrete at Workstation Area

Project #8 (11/18): Pouring New Concrete at Workstation Area

Show more
Project #8 (11/18): Starting to Install Wall Framing

Project #8 (11/18): Starting to Install Wall Framing

Update (1/20/2020):

Cambridge Project #7: Transfer Station New Build

With temperatures dipping and rain, ice, and snow moving into the region over the past month, the Cambridge team continues to make progress and move the construction of this transfer station new build forward!  The drive-in pit construction is complete; the tipping floor has been fully poured and deflector plates and special metal on pre-cast walls have been installed; bird netting and fluorescent lighting installed; the scale house has been set on the foundation and ramps are installed; the City’s water main tie in is complete; and the offices construction is complete and furniture installed.  Check back for our final photos of this project in February!   🏭🔶🛠️

#transferstation #newbuild #constructioninprocess

Previous
Next
Show more
Project #7 (1/20): Back-In Pit

Project #7 (1/20): Back-In Pit

Show more
Project #7 (1/20): Tipping Floor Poured & Deflector Plates Installed

Project #7 (1/20): Tipping Floor Poured & Deflector Plates Installed

Show more
Project #7 (1/20): Bird Netting & LED Lights Installed

Project #7 (1/20): Bird Netting & LED Lights Installed

Show more
Project #7 (1/20): Scale House Set on Foundation

Project #7 (1/20): Scale House Set on Foundation

Show more
Project #7 (1/20): Scale House Ramp

Project #7 (1/20): Scale House Ramp

Show more
Project #7 (1/20): City Water Main Tie In

Project #7 (1/20): City Water Main Tie In

Show more
Project #7 (1/20): Manager Office Completed and Furniture Installed

Project #7 (1/20): Manager Office Completed and Furniture Installed

Show more
Project #7 (1/20): Workstation Office Complete and Furniture Installed

Project #7 (1/20): Workstation Office Complete and Furniture Installed

Show more
Project #7 (10/29): View Southwest Scale Ramp Walls Looking West

Project #7 (10/29): View Southwest Scale Ramp Walls Looking West

Show more
Project #7 (10/29): View Inside Northeast Ramp Walls Pre-Backfilling for Paving

Project #7 (10/29): View Inside Northeast Ramp Walls Pre-Backfilling for Paving

Show more
Project #7 (10/29): View Northeast Ramp Formed Looking Southeast

Project #7 (10/29): View Northeast Ramp Formed Looking Southeast

Show more
Project #7 (10/29): Saw Cutting Control Joints in Apron

Project #7 (10/29): Saw Cutting Control Joints in Apron

Show more
Project #7 (10/29): Starting Apron Pour

Project #7 (10/29): Starting Apron Pour

Show more
Project #7 (10/29): Installing Lower Layer of Wire Mesh in Apron

Project #7 (10/29): Installing Lower Layer of Wire Mesh in Apron

Show more
Project #7 (10/29): Aerial of Metal Building Installation

Project #7 (10/29): Aerial of Metal Building Installation

Show more
Project #7 (9/16): Appling seal mastic on South pit wall

Project #7 (9/16): Appling seal mastic on South pit wall

Show more
Project #7 (9/16):North ramp footings

Project #7 (9/16):North ramp footings

Show more
Project #7 (9/16): Footing and wall rebar for North ramp

Project #7 (9/16): Footing and wall rebar for North ramp

Show more
Project #7 (9/16): West side push wall

Project #7 (9/16): West side push wall

Show more
Project #7 (9/16): Installing rebar for South push wall

Project #7 (9/16): Installing rebar for South push wall

Show more
Project #7 (9/16): Appling seal mastic on South pit wall

Project #7 (9/16): Appling seal mastic on South pit wall

Update (10/23):

Cambridge’s Project #6: Processing Facility Expansion

This processing facility has been moving along nicely over the past few months.  We are entering the final stage!  View some images of a filtration system at the new tipping building, conveying equipment at the residual waste building, the exterior of the tipping building construction and two video highlighting nearly completed areas in the testing phase of the project.

#processingfacility #construction #designbuild #workinprogress

Previous
Next
Show more
Project #6 (10/23): Tipping Building Construction

Project #6 (10/23): Tipping Building Construction

Show more
Project #6 (10/23): Residual Waste Building and Van Dyk Conveying Equipment

Project #6 (10/23): Residual Waste Building and Van Dyk Conveying Equipment

Show more
Project #6 (10/23): Donaldson Filtration Systems Baghouse Collectors Installed at Tipping Building

Project #6 (10/23): Donaldson Filtration Systems Baghouse Collectors Installed at Tipping Building

Show more
Processing Facility Expansion

Processing Facility Expansion

Show more
Processing Facility Expansion

Processing Facility Expansion