IN PROGRESS

  • West Hauling Company New Build
  • East Hauling Company New Build
  • Midwest Maintenance Shop Remodel
  • Midwest Hauling Company New Build

UPCOMING PROJECTS!

  • Midwest Shop Expansion
  • Midwest Transfer Station New Build
  • Material Recovery Facility New Build
  • West Processing Facility New Build

WORK-IN-PROGRESS

Progress photos from the remodel of an existing facility, addition of new buildings, and site improvements.

Update (11/29):

Cambridge’s Project #1: Hauling Company Work in Progress update

Progress, progress, progress!! Sections of the Hauling Company project are complete including the exterior lighting installation, the south lot paved and striped, and the bay floors polished.  Work continues on the fuel island and tank installation as well as the office studs and roof decking installation.  Check back here for the final progress on the Hauling Company project!  🏭🔶🛠️

Previous
Next
Show more
Project #1 (11/29): Exterior Lighting Installed

Project #1 (11/29): Exterior Lighting Installed

Show more
Project #1 (11/29): South Lot Paved and Striped

Project #1 (11/29): South Lot Paved and Striped

Show more
Project #1 (11/29): Polishing Bay Floors

Project #1 (11/29): Polishing Bay Floors

Show more
Project #1 (11/29): Fuel Island Installation Continues

Project #1 (11/29): Fuel Island Installation Continues

Show more
Project #1 (11/29): Tank Installation

Project #1 (11/29): Tank Installation

Show more
Project #1 (11/29): Office Studs and Roof Decking Installation

Project #1 (11/29): Office Studs and Roof Decking Installation

Show more
Project #1 (11/8): Fuel Island Canopy Installation Began

Project #1 (11/8): Fuel Island Canopy Installation Began

Show more
Project #1 (11/8): Fuel Island Forms Removed

Project #1 (11/8): Fuel Island Forms Removed

Show more
Project #1 (11/8): Polished Floors and Completed Bays in Addition

Project #1 (11/8): Polished Floors and Completed Bays in Addition

Show more
Project #1 (11/8): Wash Bay Floor before Seal Completed

Project #1 (11/8): Wash Bay Floor before Seal Completed

Show more
Project #1 (11/8): Exterior Fixtures and Photo Sensors Installation

Project #1 (11/8): Exterior Fixtures and Photo Sensors Installation

Show more
Project #1 (10/19): Concrete poured and control joints cut

Project #1 (10/19): Concrete poured and control joints cut

Show more
Project #1 (10/19): Sprinkler and big fan installed in shop addition

Project #1 (10/19): Sprinkler and big fan installed in shop addition

Show more
Project #1 (10/19): Red light/green light switches installed (exterior)

Project #1 (10/19): Red light/green light switches installed (exterior)

Show more
Project #1 (10/19): Wash Bay nearly completed

Project #1 (10/19): Wash Bay nearly completed

Show more
Project #1 (10/19): Equipment Room air and conduit lines installed and equipment moved in

Project #1 (10/19): Equipment Room air and conduit lines installed and equipment moved in

Show more
Project #1 (10/19): Fuel Island installation has begun

Project #1 (10/19): Fuel Island installation has begun

Show more
Project #1 (9/24): Pile of Concrete Removed from North Drive

Project #1 (9/24): Pile of Concrete Removed from North Drive

Show more
Project #1 (9/24): L.P Tank Pad Pre-Pour Bollards

Project #1 (9/24): L.P Tank Pad Pre-Pour Bollards

Show more
Project #1 (9/24): Installing Overhead Door Panels

Project #1 (9/24): Installing Overhead Door Panels

Show more
Project #1 (9/24): Working on South Overhead Door Tracks

Project #1 (9/24): Working on South Overhead Door Tracks

Show more
Project #1 (9/24): View of Conduit Bank on Westside Addition

Project #1 (9/24): View of Conduit Bank on Westside Addition

Show more
Project #1 (9/3): Overhead Door Framing

Project #1 (9/3): Overhead Door Framing

Show more
Project #1 (9/3): Power Trowel Paving

Project #1 (9/3): Power Trowel Paving

Show more
Project #1 (9/3): Pre-Paving Concrete Pour

Project #1 (9/3): Pre-Paving Concrete Pour

Show more
Project #1 (9/3): Loading out Spoils

Project #1 (9/3): Loading out Spoils

Show more
Project #1 (9/3): New Wash Bay Addition and Site Paving

Project #1 (9/3): New Wash Bay Addition and Site Paving

Progress photos from the new build of a maintenance shop.

Update (11/15):

Cambridge Project #2: Maintenance Shop Work in Progress update:

Despite the inclement weather in the area, work on the maintenance shop continues to move forward!  The metal building has been fully assembled with the walls now being installed; the office electrical & plumbing rough-ins are underway; and the parking areas continue as weather permits. 🏭🔶🛠️

Previous
Next
Show more
Project #2 (11/15): Exterior of Office Trim Started

Project #2 (11/15): Exterior of Office Trim Started

Show more
Project #2 (11/15): Interior Wall Framing and Blocking

Project #2 (11/15): Interior Wall Framing and Blocking

Show more
Project #2 (11/15): Shop View of Masonry Separation Wall

Project #2 (11/15): Shop View of Masonry Separation Wall

Show more
Project #2 (11/15): Future Parts Room View into the Future Shop

Project #2 (11/15): Future Parts Room View into the Future Shop

Show more
Project #2 (11/15): Another Section of Truck Parking Poured

Project #2 (11/15): Another Section of Truck Parking Poured

Show more
Project #2 (11/15): Progress in the Truck Parking Lot Concrete

Project #2 (11/15): Progress in the Truck Parking Lot Concrete

Show more
Project #2 (10/25): Sheeting being laid on metal building roof

Project #2 (10/25): Sheeting being laid on metal building roof

Show more
Project #2 (10/25): Site graded with mesh laid for concrete pour

Project #2 (10/25): Site graded with mesh laid for concrete pour

Show more
Project #2 (10/25): Curbs laid out on shop flooring

Project #2 (10/25): Curbs laid out on shop flooring

Show more
Project #2 (10/25): Employee parking area concrete poured and control joints cut

Project #2 (10/25): Employee parking area concrete poured and control joints cut

Show more
Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Show more
Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Show more
Project #2 (10/3): Maintenance Shop Aerial September 2018

Project #2 (10/3): Maintenance Shop Aerial September 2018

Show more
Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Show more
Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Show more
Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Show more
Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Show more
Project #2 (10/3): Brooming Concrete Employee Parking Lot

Project #2 (10/3): Brooming Concrete Employee Parking Lot

Show more
Project #2 (9/10): Office Building Parking Area

Project #2 (9/10): Office Building Parking Area

Show more
Project #2 (9/10): Placing Aggregate Base

Project #2 (9/10): Placing Aggregate Base

Show more
Project #2 (9/10): Vapor Barrier And Rebar Installation

Project #2 (9/10): Vapor Barrier And Rebar Installation

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Progress photos from the truck maintenance shop.

Update (11/21):

Cambridge’s Project #3: Maintenance Shop Work in Progress update:

Progress continues on this maintenance shop, despite the snowy weather the Cambridge team and subcontractors have encountered.  The Asphalt work continues on the southeast portion of the property; the east side overhead doors have been installed; ductwork, truck exhaust modifications, and hose reels have been installed; the HVAC equipment has been installed; and drywall in the office area has been installed.  🏭🔶🛠️

Previous
Next
Show more
Project #3 (11/21): Overhead Door Install in Existing Shop

Project #3 (11/21): Overhead Door Install in Existing Shop

Show more
Project #3 (11/21): Ductwork Installed in Existing Shop

Project #3 (11/21): Ductwork Installed in Existing Shop

Show more
Project #3 (11/21): Truck Exhaust Modifications in Existing Shop

Project #3 (11/21): Truck Exhaust Modifications in Existing Shop

Show more
Project #3 (11/21): Hose Reels Installed in Shop Addition

Project #3 (11/21): Hose Reels Installed in Shop Addition

Show more
Project #3 (11/21): Hose Reels Installed in Shop Addition

Project #3 (11/21): Hose Reels Installed in Shop Addition

Show more
Project #3 (11/21): HVAC Installed

Project #3 (11/21): HVAC Installed

Show more
Project #3 (11/21): Drywall Install in Office Renovation

Project #3 (11/21): Drywall Install in Office Renovation

Show more
Project #3 (11/2): Office Tile Demo

Project #3 (11/2): Office Tile Demo

Show more
Project #3 (11/2): New Framing Installed

Project #3 (11/2): New Framing Installed

Show more
Project #3 (11/2): Parts Room complete

Project #3 (11/2): Parts Room complete

Show more
Project #3 (11/2): Stripped Curb in Parking Lot

Project #3 (11/2): Stripped Curb in Parking Lot

Show more
Project #3 (11/2): View of the Retention Pond

Project #3 (11/2): View of the Retention Pond

Show more
Project #3 (11/2): Spreading Stone Base prior to Asphalt Pour

Project #3 (11/2): Spreading Stone Base prior to Asphalt Pour

Show more
Project #3 (10/9): Apron Grading

Project #3 (10/9): Apron Grading

Show more
Project #3 (10/9): Completed Washroom

Project #3 (10/9): Completed Washroom

Show more
Project #3 (10/9): Completed Break Room

Project #3 (10/9): Completed Break Room

Show more
Project #3 (10/9): Completed Locker Room

Project #3 (10/9): Completed Locker Room

Show more
Project #3 (10/9): Parking Lot Demo

Project #3 (10/9): Parking Lot Demo

Show more
Project #3 (10/9): Storm Water Installation

Project #3 (10/9): Storm Water Installation