IN PROGRESS

  • East Hauling Company New Build
  • Midwest Hauling Company New Build
  • Processing Facility Remodel

UPCOMING PROJECTS!

  • Midwest Shop Expansion
  • Midwest Transfer Station New Build
  • Material Recovery Facility New Build
  • West Processing Facility New Build

WORK-IN-PROGRESS

Progress photos from the new build of a maintenance shop.

Update (7/17):

Cambridge Project #2: Maintenance Shop Work in Progress update:

Moving closer and closer to this maintenance project completion!  Our photos today show the completion of the west side exterior of the maintenance shop; interior view of overhead doors installed; breakroom tables, chairs, counter and appliances; the men’s locker room washroom; and security access controls installed.

#maintenanceshop #newbuild #progress #almostcomplete

Previous
Next
Show more
Project #2 (7/17): West Side of Maintenance Shop

Project #2 (7/17): West Side of Maintenance Shop

Show more
Project #2 (7/17): Interior Overhead Doors

Project #2 (7/17): Interior Overhead Doors

Show more
Project #2 (7/17): Breakroom Tables Panoramic View

Project #2 (7/17): Breakroom Tables Panoramic View

Show more
Project #2 (7/17): Breakroom Table and Chairs

Project #2 (7/17): Breakroom Table and Chairs

Show more
Project #2 (7/17): Breakroom County and Appliances

Project #2 (7/17): Breakroom County and Appliances

Show more
Project #2 (7/17): Men's Washroom in Locker Room

Project #2 (7/17): Men’s Washroom in Locker Room

Show more
Project #2 (7/17): Security Access Controls Installed

Project #2 (7/17): Security Access Controls Installed

Show more
Project #2 (6/20): Installation of the Office Counter

Project #2 (6/20): Installation of the Office Counter

Show more
Project #2 (6/20): Shop Work Nearly Complete

Project #2 (6/20): Shop Work Nearly Complete

Show more
Project #2 (6/20): Breakroom Process of Microwaves Installed

Project #2 (6/20): Breakroom Process of Microwaves Installed

Show more
Project #2 (6/20): Concrete for Truck Plugs Poured

Project #2 (6/20): Concrete for Truck Plugs Poured

Show more
Project #2 (6/20): Holding Tank Moved into Place

Project #2 (6/20): Holding Tank Moved into Place

Show more
Project #2 (6/20): Parts Room Assembly

Project #2 (6/20): Parts Room Assembly

Show more
Project #2 (5/14): Mesh Installation for Concrete Pour

Project #2 (5/14): Mesh Installation for Concrete Pour

Show more
Project #2 (5/14): Concrete Pour Prep Work

Project #2 (5/14): Concrete Pour Prep Work

Show more
Project #2 (5/14): Concrete Pour

Project #2 (5/14): Concrete Pour

Show more
Project #2 (5/14): Parking Lot Grading Continues, Preparing for Asphalt Pour

Project #2 (5/14): Parking Lot Grading Continues, Preparing for Asphalt Pour

Show more
Project #2 (5/14): Truck Plug Installation Begins

Project #2 (5/14): Truck Plug Installation Begins

Show more
Project #2 (5/14): Restroom Sink and Backsplash Installed

Project #2 (5/14): Restroom Sink and Backsplash Installed

Show more
Project #2 (4/2): Truck Plug Conduits Installed

Project #2 (4/2): Truck Plug Conduits Installed

Show more
Project #2 (4/2): 10,000-gallon Sanitary Tank Delivered

Project #2 (4/2): 10,000-gallon Sanitary Tank Delivered

Show more
Project #2 (4/2): Exterior Shop Lighting Completed

Project #2 (4/2): Exterior Shop Lighting Completed

Show more
Project #2 (4/2): Ready for Sink Installation

Project #2 (4/2): Ready for Sink Installation

Show more
Project #2 (4/2): Lube Room Equipment Complete

Project #2 (4/2): Lube Room Equipment Complete

Show more
Project #2 (4/2): Water Heater Installed

Project #2 (4/2): Water Heater Installed

Show more
Project #2 (2/14): Roof Drain Stubs

Project #2 (2/14): Roof Drain Stubs

Show more
Project #2 (2/14): Entry Door Trim Installed

Project #2 (2/14): Entry Door Trim Installed

Show more
Project #2 (2/14): Final Door Panels Installed on the East Side

Project #2 (2/14): Final Door Panels Installed on the East Side

Show more
Project #2 (2/14): Water Lines Dug and Being Installed

Project #2 (2/14): Water Lines Dug and Being Installed

Show more
Project #2 (2/14): T-bar Grid in the Break Room Installed

Project #2 (2/14): T-bar Grid in the Break Room Installed

Show more
Project #2 (2/14): Conduits Run to the Shop

Project #2 (2/14): Conduits Run to the Shop

Show more
Project #2 (2/14): Transformer and Pad Installed

Project #2 (2/14): Transformer and Pad Installed

Show more
Project #2 (1/7): Coiling Door Installed in Parts Room

Project #2 (1/7): Coiling Door Installed in Parts Room

Show more
Project #2 (1/7): Doors, Frames & Hardware Installed

Project #2 (1/7): Doors, Frames & Hardware Installed

Show more
Project #2 (1/7): Drywall Completed

Project #2 (1/7): Drywall Completed

Show more
Project #2 (1/7): Column Framing in Parts Room

Project #2 (1/7): Column Framing in Parts Room

Show more
Project #2 (1/7): Preparing for Ceiling Grid in Break Room

Project #2 (1/7): Preparing for Ceiling Grid in Break Room

Show more
Project #2 (1/7): Enclosed Service Counter Installed

Project #2 (1/7): Enclosed Service Counter Installed

Show more
Project #2 (12/18): Aerial View of the Site and Facility Progress

Project #2 (12/18): Aerial View of the Site and Facility Progress

Show more
Project #2 (12/18): Siding Installation on Metal Building Progress

Project #2 (12/18): Siding Installation on Metal Building Progress

Show more
Project #2 (12/18): Ductwork being Installed

Project #2 (12/18): Ductwork being Installed

Show more
Project #2 (12/18): Framing Installation of Office Section

Project #2 (12/18): Framing Installation of Office Section

Show more
Project #2 (12/18): Drywall beginning to be Installed

Project #2 (12/18): Drywall beginning to be Installed

Show more
Project #2 (12/18): Masonry Work

Project #2 (12/18): Masonry Work

Show more
Project #2 (11/15): Exterior of Office Trim Started

Project #2 (11/15): Exterior of Office Trim Started

Show more
Project #2 (11/15): Interior Wall Framing and Blocking

Project #2 (11/15): Interior Wall Framing and Blocking

Show more
Project #2 (11/15): Shop View of Masonry Separation Wall

Project #2 (11/15): Shop View of Masonry Separation Wall

Show more
Project #2 (11/15): Future Parts Room View into the Future Shop

Project #2 (11/15): Future Parts Room View into the Future Shop

Show more
Project #2 (11/15): Another Section of Truck Parking Poured

Project #2 (11/15): Another Section of Truck Parking Poured

Show more
Project #2 (11/15): Progress in the Truck Parking Lot Concrete

Project #2 (11/15): Progress in the Truck Parking Lot Concrete

Show more
Project #2 (10/25): Sheeting being laid on metal building roof

Project #2 (10/25): Sheeting being laid on metal building roof

Show more
Project #2 (10/25): Site graded with mesh laid for concrete pour

Project #2 (10/25): Site graded with mesh laid for concrete pour

Show more
Project #2 (10/25): Curbs laid out on shop flooring

Project #2 (10/25): Curbs laid out on shop flooring

Show more
Project #2 (10/25): Employee parking area concrete poured and control joints cut

Project #2 (10/25): Employee parking area concrete poured and control joints cut

Show more
Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Show more
Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Show more
Project #2 (10/3): Maintenance Shop Aerial September 2018

Project #2 (10/3): Maintenance Shop Aerial September 2018

Show more
Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Show more
Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Show more
Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Show more
Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Show more
Project #2 (10/3): Brooming Concrete Employee Parking Lot

Project #2 (10/3): Brooming Concrete Employee Parking Lot

Show more
Project #2 (9/10): Office Building Parking Area

Project #2 (9/10): Office Building Parking Area

Show more
Project #2 (9/10): Placing Aggregate Base

Project #2 (9/10): Placing Aggregate Base

Show more
Project #2 (9/10): Vapor Barrier And Rebar Installation

Project #2 (9/10): Vapor Barrier And Rebar Installation

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Progress photos from the truck maintenance shop.

Update (6/21):

Cambridge’s Project #3: Maintenance Shop Work in Progress update:

Phase 2 of this Maintenance Shop Renovation is done, which means this project is fully complete!  Everything is complete including roughly 35,000 SF of new TPO membrane roofing, new parking lot striping, locker rooms, restrooms, & break rooms.  We are happy to have been project partners on this project with the facility owners!

Previous
Next
Show more
Project #3 (2/20): Above Mezzanine Emergency Lighting

Project #3 (2/20): Above Mezzanine Emergency Lighting

Show more
Project #3 (2/20): Stairwell Emergency Lighting

Project #3 (2/20): Stairwell Emergency Lighting

Show more
Project #3 (2/20): Driver's Waiting Room Door Installed

Project #3 (2/20): Driver’s Waiting Room Door Installed

Show more
Project #3 (2/20): Under-Mezzanine Sprinkler Pipe Installed

Project #3 (2/20): Under-Mezzanine Sprinkler Pipe Installed

Show more
Project #3 (2/20): Middle Lube Reel in Existing Shop Installed

Project #3 (2/20): Middle Lube Reel in Existing Shop Installed

Show more
Project #3 (2/20): Front of Building Looking West

Project #3 (2/20): Front of Building Looking West

Show more
Project #3 (12/20): East Side West Gate Installed

Project #3 (12/20): East Side West Gate Installed

Show more
Project #3 (12/20): West Side Overhead Doors Installed

Project #3 (12/20): West Side Overhead Doors Installed

Show more
Project #3 (12/20): New Lights Installed in Existing Services Bays

Project #3 (12/20): New Lights Installed in Existing Services Bays

Show more
Project #3 (12/20): Concrete Removal for New Trench Drain

Project #3 (12/20): Concrete Removal for New Trench Drain

Show more
Project #3 (12/20): Hallway Tile Installation

Project #3 (12/20): Hallway Tile Installation

Show more
Project #3 (11/21): Overhead Door Install in Existing Shop

Project #3 (11/21): Overhead Door Install in Existing Shop

Show more
Project #3 (11/21): Ductwork Installed in Existing Shop

Project #3 (11/21): Ductwork Installed in Existing Shop

Show more
Project #3 (11/21): Truck Exhaust Modifications in Existing Shop

Project #3 (11/21): Truck Exhaust Modifications in Existing Shop

Show more
Project #3 (11/21): Hose Reels Installed in Shop Addition

Project #3 (11/21): Hose Reels Installed in Shop Addition

Show more
Project #3 (11/21): Hose Reels Installed in Shop Addition

Project #3 (11/21): Hose Reels Installed in Shop Addition

Show more
Project #3 (11/21): HVAC Installed

Project #3 (11/21): HVAC Installed

Show more
Project #3 (11/21): Drywall Install in Office Renovation

Project #3 (11/21): Drywall Install in Office Renovation

Show more
Project #3 (11/2): Office Tile Demo

Project #3 (11/2): Office Tile Demo

Show more
Project #3 (11/2): New Framing Installed

Project #3 (11/2): New Framing Installed

Show more
Project #3 (11/2): Parts Room complete

Project #3 (11/2): Parts Room complete

Show more
Project #3 (11/2): Stripped Curb in Parking Lot

Project #3 (11/2): Stripped Curb in Parking Lot

Show more
Project #3 (11/2): View of the Retention Pond

Project #3 (11/2): View of the Retention Pond

Show more
Project #3 (11/2): Spreading Stone Base prior to Asphalt Pour

Project #3 (11/2): Spreading Stone Base prior to Asphalt Pour

Show more
Project #3 (10/9): Apron Grading

Project #3 (10/9): Apron Grading

Show more
Project #3 (10/9): Completed Washroom

Project #3 (10/9): Completed Washroom

Show more
Project #3 (10/9): Completed Break Room

Project #3 (10/9): Completed Break Room

Show more
Project #3 (10/9): Completed Locker Room

Project #3 (10/9): Completed Locker Room

Show more
Project #3 (10/9): Parking Lot Demo

Project #3 (10/9): Parking Lot Demo

Show more
Project #3 (10/9): Storm Water Installation

Project #3 (10/9): Storm Water Installation

Cambridge’s WIP Project #4: Maintenance Shop #4

View the final before and after  photos from the Maintenance Shop Remodel and Site

Work on the project page by clicking the image!

#designbuild #maintenanceshop #renovation #constructioncomplete

Progress photos from the remodel of a processing facility.

Update (4/24):

Cambridge’s Project #5: Processing Facility update

The smallest of our current projects took only 17 weeks to complete!  View our final photos below of the remaining dirt bring removed from the process area and the cleaned floor; installation of the east handrails from the north and south views; installation of the west handrails at the end of the pit; and the north apron concrete poured, overhead doors installed and completed.  We will have a final project page for you to view these and other images shortly so stay tuned for this final information!

Previous
Next
Show more
Project # 5 (4/24): New Floor Area Cleaned

Project # 5 (4/24): New Floor Area Cleaned

Show more
Project # 5 (4/24): Installed East Handrails (north to south view)

Project # 5 (4/24): Installed East Handrails (north to south view)

Show more
Project # 5 (4/24): Installed East Handrails (south to north view)

Project # 5 (4/24): Installed East Handrails (south to north view)

Show more
Project # 5 (4/24): Installed West Handrails at the End of the Pit

Project # 5 (4/24): Installed West Handrails at the End of the Pit

Show more
Project # 5 (4/24): North Apron Overhead Doors Complete

Project # 5 (4/24): North Apron Overhead Doors Complete

Show more
Project # 5 (3/18): Four Columns with First Coat of Paint

Project # 5 (3/18): Four Columns with First Coat of Paint

Show more
Project # 5 (3/18): Tipping Floor Rebar Installed

Project # 5 (3/18): Tipping Floor Rebar Installed

Show more
Project # 5 (3/18): Handrails at the Loading Pit Installed

Project # 5 (3/18): Handrails at the Loading Pit Installed

Show more
Project # 5 (3/18): Concrete on the East Side of the Pit

Project # 5 (3/18): Concrete on the East Side of the Pit

Show more
Project # 5 (3/18): Concrete at the South Ramp

Project # 5 (3/18): Concrete at the South Ramp

Show more
Project # 5 (3/18): Exterior View of New Coiling Door Opening

Project # 5 (3/18): Exterior View of New Coiling Door Opening

Update (5/1):

Cambridge’s Project #6: Fulcrum BioEnergy Stage 2 Expansion Managed by Cambridge Builders Inc.

Previous
Next
Show more
Fulcrum BioEnergy Stage 2 Expansion Managed by Cambridge Builders Inc.

Fulcrum BioEnergy Stage 2 Expansion Managed by Cambridge Builders Inc.

Show more
Fulcrum BioEnergy Stage 2 Expansion Managed by Cambridge Builders Inc.

Fulcrum BioEnergy Stage 2 Expansion Managed by Cambridge Builders Inc.