IN PROGRESS

  • West Hauling Company New Build
  • East Hauling Company New Build
  • Midwest Maintenance Shop Remodel
  • Midwest Hauling Company New Build

UPCOMING PROJECTS!

  • Midwest Shop Expansion
  • Midwest Transfer Station New Build
  • Material Recovery Facility New Build
  • West Processing Facility New Build

WORK-IN-PROGRESS

Progress photos from the remodel of an existing facility, addition of new buildings, and site improvements.

Previous
Next
Show more
Project #1 (11/8): Fuel Island Canopy Installation Began

Project #1 (11/8): Fuel Island Canopy Installation Began

Show more
Project #1 (11/8): Fuel Island Forms Removed

Project #1 (11/8): Fuel Island Forms Removed

Show more
Project #1 (11/8): Polished Floors and Completed Bays in Addition

Project #1 (11/8): Polished Floors and Completed Bays in Addition

Show more
Project #1 (11/8): Wash Bay Floor before Seal Completed

Project #1 (11/8): Wash Bay Floor before Seal Completed

Show more
Project #1 (11/8): Exterior Fixtures and Photo Sensors Installation

Project #1 (11/8): Exterior Fixtures and Photo Sensors Installation

Show more
Project #1 (10/19): Concrete poured and control joints cut

Project #1 (10/19): Concrete poured and control joints cut

Show more
Project #1 (10/19): Sprinkler and big fan installed in shop addition

Project #1 (10/19): Sprinkler and big fan installed in shop addition

Show more
Project #1 (10/19): Red light/green light switches installed (exterior)

Project #1 (10/19): Red light/green light switches installed (exterior)

Show more
Project #1 (10/19): Wash Bay nearly completed

Project #1 (10/19): Wash Bay nearly completed

Show more
Project #1 (10/19): Equipment Room air and conduit lines installed and equipment moved in

Project #1 (10/19): Equipment Room air and conduit lines installed and equipment moved in

Show more
Project #1 (10/19): Fuel Island installation has begun

Project #1 (10/19): Fuel Island installation has begun

Show more
Project #1 (9/24): Pile of Concrete Removed from North Drive

Project #1 (9/24): Pile of Concrete Removed from North Drive

Show more
Project #1 (9/24): L.P Tank Pad Pre-Pour Bollards

Project #1 (9/24): L.P Tank Pad Pre-Pour Bollards

Show more
Project #1 (9/24): Installing Overhead Door Panels

Project #1 (9/24): Installing Overhead Door Panels

Show more
Project #1 (9/24): Working on South Overhead Door Tracks

Project #1 (9/24): Working on South Overhead Door Tracks

Show more
Project #1 (9/24): View of Conduit Bank on Westside Addition

Project #1 (9/24): View of Conduit Bank on Westside Addition

Show more
Project #1 (9/3): Overhead Door Framing

Project #1 (9/3): Overhead Door Framing

Show more
Project #1 (9/3): Power Trowel Paving

Project #1 (9/3): Power Trowel Paving

Show more
Project #1 (9/3): Pre-Paving Concrete Pour

Project #1 (9/3): Pre-Paving Concrete Pour

Show more
Project #1 (9/3): Loading out Spoils

Project #1 (9/3): Loading out Spoils

Show more
Project #1 (9/3): New Wash Bay Addition and Site Paving

Project #1 (9/3): New Wash Bay Addition and Site Paving

Progress photos from the new build of a maintenance shop.

Previous
Next
Show more
Project #2 (10/25): Sheeting being laid on metal building roof

Project #2 (10/25): Sheeting being laid on metal building roof

Show more
Project #2 (10/25): Site graded with mesh laid for concrete pour

Project #2 (10/25): Site graded with mesh laid for concrete pour

Show more
Project #2 (10/25): Curbs laid out on shop flooring

Project #2 (10/25): Curbs laid out on shop flooring

Show more
Project #2 (10/25): Employee parking area concrete poured and control joints cut

Project #2 (10/25): Employee parking area concrete poured and control joints cut

Show more
Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Project #2 (10/25): Conduits laid and routed to the facility and fuel island (not pictured in this photo)

Show more
Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Project #2 (10/25): Metal surds and insulation material for roofing and walls of building delivered

Show more
Project #2 (10/3): Maintenance Shop Aerial September 2018

Project #2 (10/3): Maintenance Shop Aerial September 2018

Show more
Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Project #2 (10/3): Maintenance Shop Ground View of Metal Building

Show more
Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Project #2 (10/3): Maintenance Shop Employee Parking Lot Base Dry

Show more
Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Project #2 (10/3): Maintenance Shop Setting Forms in Employee Parking Lot

Show more
Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Project #2 (10/3): Maintenance Shop Concrete Pour Employee Parking Lot

Show more
Project #2 (10/3): Brooming Concrete Employee Parking Lot

Project #2 (10/3): Brooming Concrete Employee Parking Lot

Show more
Project #2 (9/10): Office Building Parking Area

Project #2 (9/10): Office Building Parking Area

Show more
Project #2 (9/10): Placing Aggregate Base

Project #2 (9/10): Placing Aggregate Base

Show more
Project #2 (9/10): Vapor Barrier And Rebar Installation

Project #2 (9/10): Vapor Barrier And Rebar Installation

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Show more
Project #2 (9/10): Placing Concrete West Shop Floor

Project #2 (9/10): Placing Concrete West Shop Floor

Progress photos from the truck maintenance shop.

Previous
Next
Show more
Project #3 (10/9): Parking Lot Demo

Project #3 (10/9): Parking Lot Demo

Show more
Project #3 (10/9): Apron Grading

Project #3 (10/9): Apron Grading

Show more
Project #3 (10/9): Storm Water Installation

Project #3 (10/9): Storm Water Installation

Show more
Project #3 (10/9): Completed Washroom

Project #3 (10/9): Completed Washroom

Show more
Project #3 (10/9): Completed Locker Room

Project #3 (10/9): Completed Locker Room

Show more
Project #3 (10/9): Completed Break Room

Project #3 (10/9): Completed Break Room