IN PROGRESS

  • Midwest Hauling Company New Build (complete)
  • Midwest Maintenance Shop Renovation & Site work (complete)
  • Processing Facility Remodel
  • Midwest Transfer Station New Build

UPCOMING PROJECTS!

  • West Container Repair Shop
  • Southwest Transfer Station New Build
  • Midwest Transfer Station New Build
  • Eastern Compactor Shop Repair
  • West Processing Facility New Build

WORK-IN-PROGRESS

Cambridge Project #2: Maintenance Shop New Build

This maintenance shop new build is complete!  Take a look at our final photos of the exterior of the maintenance shop, diesel truck plugs, interior of the maintenance shop, the services desk, parts room, lube room, offices, hallway, locker room and breakroom.  Thanks to the team and our client for making this a successful project!

Look at the project page by clicking the image!

#maintenanceshop #newbuild #constructioncomplete

Cambridge Project #4: Maintenance Shop Renovation & Site Work

View the final before and after  photos from the Maintenance Shop Renovation and Site Work on the project page by clicking the image!

#designbuild #maintenanceshop #renovation #constructioncomplete

Update (10/23):

Cambridge’s Project #6: Processing Facility Expansion

This processing facility has been moving along nicely over the past few months.  We are entering the final stage!  View some images of a filtration system at the new tipping building, conveying equipment at the residual waste building, the exterior of the tipping building construction and two video highlighting nearly completed areas in the testing phase of the project.

#processingfacility #construction #designbuild #workinprogress

Previous
Next
Show more
Project #6 (10/23): Tipping Building Construction

Project #6 (10/23): Tipping Building Construction

Show more
Project #6 (10/23): Residual Waste Building and Van Dyk Conveying Equipment

Project #6 (10/23): Residual Waste Building and Van Dyk Conveying Equipment

Show more
Project #6 (10/23): Donaldson Filtration Systems Baghouse Collectors Installed at Tipping Building

Project #6 (10/23): Donaldson Filtration Systems Baghouse Collectors Installed at Tipping Building

Show more
Processing Facility Expansion

Processing Facility Expansion

Show more
Processing Facility Expansion

Processing Facility Expansion

Update (10/29):

Cambridge WIP Project #7: Transfer Station New Build

As we’ve moved into the fall weather, the progress on this transfer station continues to progress and move forward!  Our progress photos include an aerial of the metal building installation; installation of the mesh layers, concrete pour and saw cutting control joints into the apron as well as forming ramps, creating walls, and pouring concrete for the scale ramp walls.

#transferstation #newbuild #constructioninprocess

Previous
Next
Show more
Project #7 (10/29): View Southwest Scale Ramp Walls Looking West

Project #7 (10/29): View Southwest Scale Ramp Walls Looking West

Show more
Project #7 (10/29): View Inside Northeast Ramp Walls Pre-Backfilling for Paving

Project #7 (10/29): View Inside Northeast Ramp Walls Pre-Backfilling for Paving

Show more
Project #7 (10/29): View Northeast Ramp Formed Looking Southeast

Project #7 (10/29): View Northeast Ramp Formed Looking Southeast

Show more
Project #7 (10/29): Saw Cutting Control Joints in Apron

Project #7 (10/29): Saw Cutting Control Joints in Apron

Show more
Project #7 (10/29): Starting Apron Pour

Project #7 (10/29): Starting Apron Pour

Show more
Project #7 (10/29): Installing Lower Layer of Wire Mesh in Apron

Project #7 (10/29): Installing Lower Layer of Wire Mesh in Apron

Show more
Project #7 (10/29): Aerial of Metal Building Installation

Project #7 (10/29): Aerial of Metal Building Installation

Show more
Project #7 (9/16): Appling seal mastic on South pit wall

Project #7 (9/16): Appling seal mastic on South pit wall

Show more
Project #7 (9/16):North ramp footings

Project #7 (9/16):North ramp footings

Show more
Project #7 (9/16): Footing and wall rebar for North ramp

Project #7 (9/16): Footing and wall rebar for North ramp

Show more
Project #7 (9/16): West side push wall

Project #7 (9/16): West side push wall

Show more
Project #7 (9/16): Installing rebar for South push wall

Project #7 (9/16): Installing rebar for South push wall

Show more
Project #7 (9/16): Appling seal mastic on South pit wall

Project #7 (9/16): Appling seal mastic on South pit wall

Update (11/18):

Cambridge WIP Project #8: Compactor Repair Shop Modifications

This project involves a few different aspects, all of which have been moving along over the last few months!  View our photos of the completed concrete demolition, new concrete ramps & slabs, and new wall framing.  Continue to check back here for the next set of photos of this Compactor Repair Shop Modifications project!  🏭🔶🛠️

#compactor #repair #paintbooth #rampslab #newwallframe #constructioninprocess

Previous
Next
Show more
Project #8 (11/18): Demolition & Removal of Existing Concrete for New Workstations

Project #8 (11/18): Demolition & Removal of Existing Concrete for New Workstations

Show more
Project #8 (11/18): Preparing Subgrade for New Concrete Ramp

Project #8 (11/18): Preparing Subgrade for New Concrete Ramp

Show more
Project #8 (11/18): Demolition & Removal of Existing Concrete for New Ramp

Project #8 (11/18): Demolition & Removal of Existing Concrete for New Ramp

Show more
Project #8 (11/18): Pouring New Concrete Ramp

Project #8 (11/18): Pouring New Concrete Ramp

Show more
Project #8 (11/18): Infill of Existing Pit

Project #8 (11/18): Infill of Existing Pit

Show more
Project #8 (11/18): New Slab Poured at Storage Area

Project #8 (11/18): New Slab Poured at Storage Area

Show more
Project #8 (11/18): Pouring New Concrete at Workstation Area

Project #8 (11/18): Pouring New Concrete at Workstation Area

Show more
Project #8 (11/18): Starting to Install Wall Framing

Project #8 (11/18): Starting to Install Wall Framing