Project Name: Tennessee Transfer Station Repairs

Project Scope: Tipping Floor Replacement & Repairs

Timeframe: Two (2) 3-day periods (four days of shut down time, 2 Fridays & 2 Saturdays); Six (6) days total

Description: Remove and replace approximately 15,000 sq. ft. of tipping floor.

Transfer Station Tipping Floor Repair, Step-by-Step

Previous
Next
Show more
Step 1: Floor Demo Prep at Tennessee Transfer Station

Step 1: Floor Demo Prep at Tennessee Transfer Station

Show more
Step 1: Floor Demo Prep at Tennessee Transfer Station

Step 1: Floor Demo Prep at Tennessee Transfer Station

Show more
Step 2: Reinforcement with Wear Indicators at Tennessee Transfer Station

Step 2: Reinforcement with Wear Indicators at Tennessee Transfer Station

Show more
Step 2: Reinforcement with Wear Indicators at Tennessee Transfer Station

Step 2: Reinforcement with Wear Indicators at Tennessee Transfer Station

Show more
Step 3: Pour Concrete at Tennessee Transfer Station

Step 3: Pour Concrete at Tennessee Transfer Station

Show more
Step 3: Pour Concrete at Tennessee Transfer Station

Step 3: Pour Concrete at Tennessee Transfer Station

Show more
Step 4: Completed Concrete at Tennessee Transfer Station

Step 4: Completed Concrete at Tennessee Transfer Station

Show more
Step 4: Completed Concrete at Tennessee Transfer Station

Step 4: Completed Concrete at Tennessee Transfer Station